Project Schedule
Schedule is preliminary and subject to change.
Design Schedule
Project Kick-off: 02.07.2020
Schematic Design Submission: 04.22.2020
Design Development Submission: 07.31.2020
Construction Document Submission: 11.06.2020
Bidding (tentative schedule)
Bid advertisement for Construction: October 2021
Bid Opening: February 11, 2022 Bid Comparison Document
Construction Award: March/April 2022
Pre-construction Meeting/Notice to proceed: April 2022
Building Construction (~18 months duration)
Beginning of site work: June 2022
Building Envelope Completion/Climate Control Established: ~April 2023
Beginning of Interior work: ~September 2023
End of Construction: ~February 2024