Project Schedule

Schedule is preliminary and subject to change.

Design Schedule

Project Kick-off: 02.07.2020
Schematic Design Submission: 04.22.2020
Design Development Submission: 07.31.2020
Construction Document Submission: 11.06.2020

Bidding

Bid advertisement for Construction: May 2021
Bid Opening/Construction Award: June 2021-August 2021
Pre -construction Meeting/Notice to proceed: 09.01.2021

Building Construction (18 months duration)

Beginning of site work: September 2021
Building Envelope Completion/Climate Control Established: September 2022
Beginning of Interior work: October 2022
End of Construction: 01 March 2023